Indramayu Coal-Fired Power Station: Port Facility Dredging

PT Pembangkitan Jawa Bali · Indramayu, West Java

PROJECT OVERVIEW

Maintenance dredging of the channel and port basin to address rapid sedimentation, with a dumping site approximately 8 nautical miles offshore.

280,000 m³ (channel); 1,205,000 m³ (basin)

Main volume

​

Equipment Deployed

Clamshell dredger

1

Split hopper barge

2

TSHD Serang

3

Business line

Client

Dredging & Reclamation

Location

PT Pembangkitan Jawa Bali

Period

Indramayu, West Java

January 2018 – October 2018

Documentation

Project documentation.

p28-2.jpg
p28-2.jpg
p28-2.jpg

Related projects

Other Dredging & Reclamation projects.

p28-2.jpg

Patimban Port Development Project (II): Temporary Dredging Works

Patimban, Subang, West Java

September 2019 – December 2019

p28-2.jpg

Kaltim 2×100 MW CFSPP Project: Dredging Works

Bontang, East Kalimantan

July 2018 – March 2019

p28-2.jpg

PLTU 2 Jateng Adipala: Seawater Intake and Jetty Dredging

Cilacap, Central Java

March 2019 – June 2019