East Kalimantan Coal Fired Steam Power Plant (CFSPP) jetty construction ​

East Kalimantan 2X125MW CFSPP Project

  • Location: Bontang, Kalimantan Timur

  • Client: China Chengda Engineering Co. Ltd.

  • Equipment: Clamshel GJ 701 dan Split Barge GJ 501, GJ 502

  • Work method: Pengerukan Temporary Jetty yang materialnya di buang ke laut lepasa dengan jarak buang sekitar 12 nautical mile dan pelaksanaan konstruksi jetti.

  • Volume: 128.000 m3

  • Work period: 19 Juni 2017 – 05 Agustus 2018

  • Project value: IDR21,049,808,000

  • Status: Finished